The Challenge
The project demanded pinpoint accuracy to position 42-tonne bridge sections within a 50mm tolerance over live traffic lanes. Work was restricted to overnight closures with tight 6-hour windows.
Our Solution
D.M. Cranes deployed a 300-tonne Liebherr with a tandem lift configuration. Our appointed person developed a comprehensive lift plan incorporating real-time weather monitoring and a dedicated banksmen team to guide each section into place.
The Result
All four sections were placed ahead of schedule with zero incidents. The motorway reopened on time each morning, and the client commended the team for exceptional safety standards.